Temporary Take, Temporary Damages: Virginia Court of Appeals Limits Eminent Domain Claims in El-Rashed v. Commissioner of Highways
The Court of Appeals of Virginia issued an opinion giving condemning authorities welcome clarity on a recurring issue: landowners who try to use a temporary construction easement as a vehicle to recover for the claimed effects of an entire public project. In Omar Mohammad El-Rashed, et al. v. Commissioner of Highways, 2026 WL 3399756 (Nov. 10, 2026), the Court of Appeals affirmed the Fairfax County Circuit Court’s exclusion of a landowner appraiser’s nearly $500,000 “project damages” opinion. Specifically, it held that when the take is temporary, recoverable damages to the residue must be caused by the temporary taking itself.
The Facts About El-Rashed: A Ten-Foot Strip and a Half-Million-Dollar Claim
The landowners owned a home whose rear yard backed up to a VDOT right-of-way, a sound wall, and I-495. In March 2023, as part of the I-495 expansion, the Commissioner recorded a certificate of take for a temporary construction easement (TCE) over a strip less than ten feet wide totaling 1,458 square feet. This was roughly seven percent of the 20,198-square-foot parcel. VDOT valued the TCE at $29,700, which included $1,500 for trees and vines.
The landowners’ appraiser placed the TCE’s “rental value” at $53,495 but went much further, opining that the TCE and the highway project together would permanently reduce the value of the entire property by just under $500,000. His reasons were the loss of trees, the reconstruction of the sound wall closer to the home, and the proximity of the new I-495 travel lanes.
The Commissioner moved in limine to exclude that testimony, arguing that the only public use at issue was the TCE, not the entire I-495 project. The circuit court agreed. It barred testimony about damages “flowing from the overall roadway project” “shared by the entire public,” and as to non-compensable factors including loss of buffer trees on VDOT’s property or construction noise, vibration, and dust. The parties then settled the value of the TCE at $29,700, and the landowners preserved their right to appeal the evidentiary ruling.
The Holding
The Court of Appeals affirmed on every issue. Four parts of the analysis matter most to condemnors.
1. The relevant “public use” is the interest acquired, not the entire project
The landowners argued that the certificate of take, petition, and the Commissioner’s admissions defined the public use as the entire I-495 project. The court rejected that reading. Neither the certificate nor the petition used the words “public use.” Instead, the take was described as “in conjunction with” the I-495 work and “required for” the narrower purpose of constructing cut and fill slopes. The court treated that drafting as meaningful: the public use was the movement of equipment in and out of the easement area, not construction of the highway.
2. The 2019 amendments to Virginia Code § 25.1-230 did not expand residue damages
The landowners relied heavily on the 2019 amendment to Virginia Code § 25.1-230 directing consideration of “everything a buyer and seller in the marketplace would reasonably consider, including the public use for which the property is being acquired.” The court held that those amendments reflect no intent to change the law on valuation and damages outside of consideration of lost profits and lost access. It reached that result by reading the 2012 constitutional amendment, which left only “lost profits” and “lost access” for legislative definition, together with the presumption against changing the common law and the duty to construe statutes consistently with the Constitution. Because the property was “acquired” only temporarily, the relevant public use was, by definition, limited to the period of the temporary acquisition.
3. Damages must be “caused by the taking,” and here the taking was temporary
Applying the plain language of Article I, § 11, which defines just compensation to include “damages to the residue caused by the taking,” the court reasoned that the only property taken was the TCE, so recoverable residue damages are those caused by the TCE. Due to the temporary nature of the taking, damages to the residue are “necessarily also measured in temporary terms.” The Court clarified that the ruling does not categorically bar permanent damages, but any claimed permanent diminution must be causally attributable to the temporary taking rather than the larger public project. Under Virginia common law, residue damages from the overarching public use have been awarded only when part of the property is taken permanently.
4. Project-wide harms are neither “direct” nor “special”
Drawing on Livingston v. VDOT, 284 Va. 140 (2012), and Byler v. Virginia Electric & Power Co., 284 Va. 501 (2012), the Supreme Court reiterated that damage to a property right is compensable only if it flows “directly” (physically to the corpus or an appurtenant right) and “specially” (in a manner not common to the public at large). The landowners’ claimed permanent losses failed both tests: (1) they flowed from the I-495 project as a whole, not from the easement, and (2) they were shared by all nearby landowners.
Why El-Rashed Matters for Condemning Authorities
- It forecloses “project damages through the back door.” A temporary easement does not open the door to valuation testimony about the permanent effects of the entire improvement, unless those effects can be shown to flow directly from the temporary taking itself.
- It neutralizes a broad reading of the 2019 amendments. Landowners frequently cite the “everything a buyer and seller would reasonably consider” language to expand residue claims. El-Rashed holds that language is circumscribed by the temporary nature of the taking and did not change the common law or Constitution beyond lost profits and lost access.
- It reaffirms the “direct and special” test. Generalized harms common to a corridor, such as traffic proximity, noise, and loss of a visual buffer, remain non-compensable after the 2012 constitutional amendment, which the Supreme Court of Virginia has said “did not add any [new] sticks” to the bundle of property rights.
El-Rashed confirms a clear line: when the condemning authority takes a temporary easement, it pays for the temporary interest and the harms that interest causes, not for the claimed permanent effects of the public improvement that neighbors share alike. A landowner cannot convert a temporary taking case into a claim for compensation based on the broader impacts of the public project unless those impacts are directly attributable to the temporary property interest acquired. As the Supreme Court has long put it, just compensation must be “just to the condemnor and condemnee alike,” and a landowner “is entitled to ‘just compensation’ but not to bonus compensation.” Condemning authorities facing project-wide residue claims on temporary takes now have a published Court of Appeals decision squarely on point.